Building Update 8- Paint!

We are sorry that it has been a little while since we last updated you on the progress at 104. We are now in a period of overlap as the construction work nears completion and the finishing’s side of the works start. Doors All the internal doors have now been hung and look fantastic. The […]

,

Just One Natural Evangelism Course

Just One Natural Evangelism Course   The command from Jesus is for each and everyone of us to be witnesses (Acts 1:8). – When did you last lead someone to the Lord? – Have you ever found yourself not being able to progress a conversation further with friends or family? – Are there people in […]

,

Building Update 7- Toilets!

This last couple of weeks has seen some different trades people start for the first fix phase for trades, including electrical and plumbing. Planning Our Non-Material Amendment to Chichester District Council is now submitted for consideration. As a reminder this is for some very minor changes to the doors and glazing at the front of […]

Youth Worker Job

  Youth Worker Job I am writing to you to let you know about a key staffing opportunity we have at Revelation Family Church in Chichester. We are looking for a full time Youth Worker to join our staff team over the next two months. Our youth work has grown significantly in the past five […]

Building Update 6 – Progress

Another three weeks have passed on our building works with lots of progress continuing to be made on a weekly basis. The sound proofing in the main hall is now nearly complete. Fundraising In the last month we have taken on a consultant fundraiser to help us raise the funds still required for the overall […]

JOB OPPORTUNITY

  We are recruiting for a new part time position at Revelation Family Church to join our staff team. The role of a Community Development Worker will be working to help bring our new building and the vision we have, to life. You can download the Job Pack here Community Development Worker Job Pack 2019 V3

Building Update 5 – And Then There Were Walls…

The Drylining team have continued to work hard this week completing the insulation of both the ceiling’s spaces and external wall. This is to make sure we keep the noise we generate from all the activities inside the building. We also saw the start of the construction of the main hall with the walls going […]

Building Update 4 – On Schedule

Things continue to develop well on site at 104 The Hornet. We are pleased to say that we remain on schedule with the programme of works as we completed our first month. This last week has seen the dry liners start work. They are currently focused on all the ceilings and external walls and this […]

Building Update 3- Phase One Done!

Phase One Done! It has been a solid 2 weeks of work on site at 104 The Hornet with the steel construction team focused around phase one of our refit to install the internal steel structure required to hold the sound proofing we need. Today that team completed the internal steelwork right on schedule and […]