This last couple of weeks has seen some different trades people start for the first fix phase for trades, including electrical and plumbing.

Planning

Our Non-Material Amendment to Chichester District Council is now submitted for consideration. As a reminder this is for some very minor changes to the doors and glazing at the front of the building. We have been informed that should hear back from the council officers regarding our submission by the end of October.

Finishing

Our wonderful Building Team are now focusing on all the finishes around the different parts of the building. This includes doors, flooring, wall colours etc. This is both exciting and encouraging as it shows the progress being made at the end of our twelfth week of work.

Next steps

The first coats of paint will start in some of the main spaces next week and the air handling units are due to arrive in the next two weeks. The structure and platform for these large units is being built into a space in the roof.

 

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *