Things continue to develop well on site at 104 The Hornet. We are pleased to say that we remain on schedule with the programme of works as we completed our first month.

This last week has seen the dry liners start work. They are currently focused on all the ceilings and external walls and this will help create the acoustic seal needed so we don’t disturb our new neighbours once we are in occupation. This aspect of the build should be completed by the end of the month. Adding the ceilings in some areas has also started to give the first feel for some of the spaces we are creating and it is exciting seeing it take shape.

This last week we also had successful site visits from our Acoustic and Health and Safety Consultants to check in on our progress.